The dates below reflect milestone dates for the Church Avenue Paving Project.
9/21 – Pre Pre Construction Held with CFE, Inc. (Contractor).
9/27 – Electronic Message Boards will be deployed on either end of the project advertising public meeting date.
10/11 - Pre Construction and Utility Coordination meeting to be held in Commission Chambers
10/11 – Public Meeting in the Community Building at 6:00 PM. Opportunity for the public to meet with Contractor/Engineer to discuss Maintenance of Traffic (MOT) and related concerns.
10/12 - Electronic Message Boards will be deployed on either end of the project notifying the construction start date.
10/25 – Construction begins.